Home Page > News > An Off-site Infrastructure of the “Bogoslovsky” Industrial Park Will Be Completed Soon

An Off-site Infrastructure of the “Bogoslovsky” Industrial Park Will Be Completed Soon

95% of water supply infrastructure for drinking and industrial purposes has already been completed. 

Household and rainwater sewage systems have been fully mounted as well. The developer has started a construction of the facade and roof of the gas boiler room with all the boilers already installed.

Outdoor infrastructure is also including high voltage network and communications network. Connecting the Park to the networks will be fully completed by the Q1 of 2017.

Construction of the Indoor infrastructure has been already started and going on according to the confirmed schedule. Expected completion of this stage is the Q4 of 2017. Despite of the heavy frost at the beginning of the year 10% of planned work have been completed in the “Bogoslovsky” Park including water supply and sewage infrastructure.

Please visit the website of the Industrial Park for details 

12 January 2017, 17:00